Custom wardrobe and decoration before and after the main material matters needing attention


people were decorating the house, they had no idea when the construction site was going on and which main materials needed to be bought. As a result, the construction period was delayed and everything was pushed out. The whole thing was a "busy".
Now, Xiao Bian will tell you the order of the main materials entering the site. If you have a number in your heart, you will not be in a hurry. Customization and installation time of
cabinet:
start to enter the site to measure the initial drawing for water and electricity. at this time, the main purpose is to set the location of water and electricity.
Wait until the bricks are pasted and the cabinet drawings are printed before starting the production. The construction period is 25-30 days. If solid wood door panels are selected, the time will be longer. And the installation is to wait until the top ceiling is ready to install. During installation, pay attention to bringing the smoke machine, stove and basin to the site.
cabinet: it can be installed after the ceiling is installed. kitchen appliances and essential items that need to be present at the same time include: smoke machine, stove, disinfection cabinet, sink, etc.
gas stove, smoke machine, sink, embedded disinfection cabinet, etc. need to provide the opening size before making the cabinet.
sanitary ware positioning and installation time:
start the required size to determine the size of the placement position. Squat toilet water tank bathtub shower room tile into the field.
bathroom cabinet:
shower pendant wall tiles will enter the site after being pasted. If there are special main materials such as Wei Xili or intelligent toilet, the socket should be reserved in advance, and the strong toilet or faucet should be brought to the scene.
Precautions before and after Customizing Wardrobe and Decorating Main Materials (Figure 2) Measurement and Installation Time of
Doors and Windows: After
bricklayers enter the site to level the ground, the door opening and window shall determine the measurement size. The production period of
kitchen and bathroom door shall be 10-15 days (when bricklayers are pasted, a brick shall be reserved, and the brick near the door opening shall be pasted for closing after installation).
bedroom wooden door production period of 30-40 days. After the two putty on the wall surface is scraped, the production period of ordinary glass for installing the
window of the set door is 5-7 working days, and the toughened glass is 12-15 working days. After installation, the selection and installation time of the
floor tile can be started after the floor tile needs to be determined with the designer. After the bricklayer enters the site to level the ground, the brick enters the site to pave and generally needs caulking with caulking agent. At the same time need to prepare floor drain. If there is a shower partition or shower room, the shower stone should be taken to the site and buried together when the master pasted the tiles. Measurement and delivery time of
stone: when
floor tiles enter the site, measure the size of the doorsill stone. at the same time, measure the size of the windowsill and deliver it together with the doorsill stone to save freight. light-colored stone needs white cement.
Installation Time and Precautions for Kitchen and Sanitary Ceiling: After
bricks are pasted, the kitchen and sanitary ceiling can be hung, and at the same time, the flue duct, bath heater, lighting, ventilation, etc. of the hood can be taken to the site for opening holes. Note that if the toilet is equipped with wind heating during the early stage of wire installation, 7 6 groups of wires and 4 3 groups of wires for single wind heating shall be reserved. Measurement and installation of
bathroom partition: measure the size of
brick after pasting, the construction period is 15 days, the high temperature is delayed, and the bathroom partition is installed after the ceiling is installed.
wall paint brushing time:
putty scraping brush primer paint. Generally, one bottom and two sides. If the wall needs to be colored, the color should be selected in advance.
wallpaper:
putty scraped, top primer surface painted, wall base film, 3-7 days can be pasted wallpaper.
What needs to be explained here is that if you want to use wallpaper, you need to choose it 15-25 days in advance. Most of the wallpaper is shipped back from the factory, so you must reserve sufficient logistics time.
liquid wallpaper or diatom mud or shell coating:
putty bottom paint flower; Can be painted at the bottom; Can also only do the measurement and installation of flower
furniture:
wall can be measured after leveling the floor, and the customized construction period is 25-45 days. Can do wardrobe, bookcase, shoe cabinet, TV cabinet, computer desk bed and other
switch installation and attention:
wall paint after installation. Each switch or socket is independently packaged, so install one and open one. If there is an error, it can be exchanged without affecting the second sale. Installation of
lamps:
top surface finish is finished and installed.
Installation of drying racks:
It is generally recommended to install before check-in, because the warranty of the automatic rack is only one year.
If there is a suspended ceiling, the height of the suspended ceiling should not exceed 30mm.
If a fixed clothes rail is installed, it should be prepared to go to the site when the ceiling is suspended, and the master should install it together when lifting the items. Installation of
hardware:
pull basket cabinet to the site before installation; Lock set door to the site before installation; Hinge handle furniture to the site before installation. Installation of
electrical appliances:
kitchen electrical cabinets are taken to the site before installation; air conditioning decoration is completed and delivered to the site. Measurement and installation of
invisible screen window and protective net: after
brick is pasted, the size can be measured before curtain installation, and the construction period is 5-7 days.
activated carbon:
placed in cabinets, wardrobes. Burst under the hot sun can be reused.